Abstract:
World Construction Industry is one of the most booming industries in the world. It
contributes 10% of the global GDP to the tune of $4.6 Trillions. It employs almost 7% of the
total employed persons and, consumes around 40% of the total energy. The Pakistani
construction sector has displayed impressive growth of 9%. The industry is forecasted to
reach PKR 420.33bn (US$6.04bn) by 2012 with 2.52% contribution to GDP over a period of
two years. Cost overrun and delay are very frequent phenomenon and is generally associated
with nearly all projects in the world especially in developing countries. Generally 71 percent
of construction projects suffer from cost/time overrun in the world with an average cost
overrun of 43%.
The ranking of 25 factors causing cost overrun and delay in construction projects
considered in this study was made on the basis of mean value of impact which was
determined from 65 project data file and 65 executive’s opinion on structured instrument.
The factor of “Inconsistent Cash Flow” was the most significant factor with impact value of
7.78 in severe category and Weather Severity was the least significant factor with impact
value of 3.40 in moderate category. In this study 65 projects of different departments
executed by Frontier Works Organization (FWO) were considered which include 48
completed and 17 running projects. FWO is one of the biggest construction organizations of
Pakistan with a financial worth of Rs.36 billions and annual turnover of Rs.22 Billions
working all over Pakistan and abroad. Out of 65 selected projects, 38 were roads projects, 12
infrastructure and development projects (private sector) and 15 projects of Government
Departments (Railway, WAPDA, Structures, Irrigation/ Power, Airports &Telecomm). Out
of 65 projects, only 7 projects were completed within budget thus showing that 90 %
projects are suffering from cost variation including 48 i.e. 74% projects over running cost
and 10 i.e. 15% projects under running cost due to scope reduction. Only 2 projects were
completed on planned schedule thus showing that 97% of projects were suffering from
delay. Overall average cost overrun was 28.27% with an average delay of 2.1 years per
project. The highest cost overrun has been observed in projects of Government Departments
i.e. 37.59% and highest delay per projects was observed in roads projects i.e. 2.3 years per
project.
The public/private organizations, regulatory bodies, financing institutions and government
should control the financing, planning, management and technical aspects of projects to
minimize the cost/time overrun. Planning before the finalization of projects and before
execution is essential by client, consultant and contractor to avoid any unforeseen and
changes/additions in design and scope. All efforts should be made to acquire land and
resources before commencement and qualified staff should be employed by all client,
consultant and contractor organization avoiding all kind of fraud, corruption, kick backs and
contract rigging by incorporating fair approach for fair work for a fair completion overrun in
construction projects in Pakistan.