Abstract:
This present study is meant to plan and analyze the
existing sewerage system of North colony (Risalpur)
and suggest some corrective measures and design a
proposed plan for waste water treatment.
The proposed design incorporated had two
options
o Option 1: Making of Trickling filters
coupled with Grit Chamber
o Option 2: Making of an exclusive Septic
Tank
Option 2 is one of the best method of treatment
according to conditions of Risalpur Cantt. Design
of septic tank is recommended due to following
reasons:
o It's cleaning period is 6-12
months, so labour cost is less.
o Requires no professionals.
o After treatment, septic tank effluent will be
deposed to soakage pit.
o Sludge will be removed after 6-12 months.
o More over, according to our cost
estimation this method of treatment had
least cost.